Planned Capital Improvement Projects

2023 Construction Projects

1. Shakertown Road Widening 

Project Description: The project generally consists of the following components:

  • The widening of Shakertown Road to three lanes, along with the installation of curb, gutter, and storm sewer between N. Fairfield Road and Carthage Drive.
  • The installation of an eight-foot wide path along the north side of the roadway and a five-foot wide sidewalk along the south side of the roadway.
FundingOPWC Grant AssessmentLocal Total 
Construction$900,000$150,000$850,000 $1,900,000


Status: The construction contract has been awarded and the contractor is currently scheduled to begin work in early 2023.         

2. Grange Hall Road Widening; PID No. 106222

Project Description: The project generally consists of the following components:

  • The widening of Grange Hall Road to three lanes along with curb, gutter, and storm sewer improvements between Kemp Road and Summerfield Drive.
  • The installation of an eight-foot wide path along the west side of the roadway.
  • The installation of a five-foot sidewalk along the east side of the roadway.
Funding OPWC Grant Federal LocalTotal
Construction$868,000$2,247,000$1,185,000$4,300,000


Status: This project is scheduled to be advertised for bids in January 2023, with a planned construction start date in the spring of 2023.

3. Grange Hall Road Resurfacing Project; PID No. 117123

Project Description: This project consists of the milling and resurfacing of the portion of Grange Hall Road between Shakertown Road and Indian Ripple Road. The construction drawings for this project will be prepared by Engineering Division staff. 

FundingFederalLocal Total
Construction$391,716$258,284$650,000


Status: Plan preparation by Engineering Division staff is currently underway. The final plans are due to be submitted to ODOT in June, with construction planned for the fall of 2023. Construction may be delayed due to Greene County water main installation work along Grange Hall Road planned for 2023.

4. N. Fairfield Road Resurfacing Project 

Project Description:    This project includes the milling, pavement repairs, and resurfacing of N. Fairfield Road between Commons Blvd. and New Germany-Trebein Road. This project also includes vehicle detection upgrades at the four traffic signals within the project limits.

Funding LocalTotal
Construction $1,700,000$1,700,000


Status: The project construction drawings are scheduled to be completed in December of 2022, with project bidding planned for January 2023.

5. Willowcrest Stormwater Improvements

Project Description: This project includes the construction of two storm water retention facilities and other related drainage improvements to abate existing flooding issues in the area surrounding Willowcrest Road.    

FundingFederal (ARPA Funds)LocalTotal
Construction$1,800,000$200,000$2,000,000


Status: The design work for this improvement started late in 2022 and is expected to continue into the fall of 2023. It is anticipated that this project will be advertised for bids and awarded in late 2023, with construction beginning in early 2024.

6. Vineland Trail Ditch Restoration

Project Description: This project entails the restoration of the existing public drainage ditch that runs behind multiple back yards in the vicinity of Vineland Trail. The ditch restoration will include the installation of erosion control measures as well as the reestablishment of the eroded channel.            

FundingFederal (ARPA Funds)LocalTotal
Construction$1,575,000$175,000$1,750,000


Status: The design work for this improvement started late in 2022 and is expected to continue into the fall of 2023. It is anticipated that this project will be advertised for bids and awarded in late 2023, with construction beginning in early 2024.

7. Golf Course Channel Restoration

Project Description: This project entails the restoration of the drainage channels along hole number 9 and hole number 11 at the Beavercreek Golf Club.  

FundingFederal (ARPA Funds)LocalTotal
Construction$225,000$25,000$250,000


Status: The design work for this improvement started late in 2022 and is expected to continue into the fall of 2023. It is anticipated that this project will be advertised for bids and awarded in late 2023, with construction beginning in early 2024.

8. Kemp Road Widening (Freddy's)

Project Description: This project entails the widening of Kemp Road to construct a new westbound left turn lane at the entrance to the proposed Freddy’s Frozen Custard site, just to the east of the existing Speedway.   

FundingLocalTotal
Construction$300,000$300,000


Status: The design work for this improvement is planned to begin in early 2023. The plans are scheduled to be completed by the fall of 2023, with construction planned to begin in either late 2023 or early 2024.

Click here to view capital improvement projects planned for 2023 through 2027.